The direct answer

Create a room-by-room level schedule before removal begins. Record the existing finished level, proposed finish, product thickness, bedding or adhesive, underlay, preparation allowance and target transition at every doorway. Then test the combined build-up against doors, balcony thresholds, kitchen plinths, bathroom entries, skirtings and fixed joinery. The objective is not automatically to make every room identical in height. It is to choose where levels should align, where a controlled transition is acceptable and how drainage, accessibility, acoustic and building requirements will be respected. Exposed substrate conditions can refine the plan, but they should not be the first time the team discusses levels.

    Measure a network of levels, not one room

    A single dimension near the entrance does not describe an apartment floor. Survey representative points in every room and at each threshold, then relate them to a stable project datum. Older screeds may vary, and previous finishes may conceal local patches or ramps. Note changes at wet areas, balconies and service zones without assuming what lies below. The survey should also record door-leaf clearances, frames, skirting heights, built-in cabinetry, appliance openings and any floor sockets. This creates a map of consequences rather than a list of material thicknesses.

    • Use one agreed datum across the apartment
    • Record both sides of every doorway
    • Measure under doors and beside fixed joinery
    • Flag areas where the substrate is unknown
    • Keep photos linked to room references

      Compare complete systems rather than finish samples

      A timber board, porcelain tile or stone sample shows only the visible layer. The installed height also depends on preparation, levelling, membranes, underlays, adhesives and fixing method. Ask each supplier for the full proposed build-up and tolerances in writing. If products are not yet selected, use clearly labelled planning allowances and update the schedule before ordering. Avoid solving a mismatch by reducing a layer that performs another job. Acoustic treatment, waterproofing and substrate preparation are functional components, not spare millimetres to remove for convenience.

        Give every threshold a deliberate detail

        Thresholds are where independent room decisions become one apartment. Review the direction of approach, change in material, change in height, door position and visibility from adjoining spaces. A transition strip may be appropriate, but it should not be used to disguise an avoidable planning error. Align junctions with door leaves where possible so closed rooms read cleanly. At open-plan boundaries, use furniture lines or architectural edges rather than arbitrary cuts. Where accessibility is relevant, review level changes and transition profiles against the applicable project requirements and official guidance.

            Planning example

            Planning example: a fictional two-bedroom apartment will combine engineered timber in living spaces, porcelain in the kitchen and a retained stone entrance floor. Early samples suggest similar thicknesses, but the complete systems differ because the timber includes an acoustic underlay and the porcelain zone needs more substrate correction. The first layout would leave a raised kitchen edge across the main circulation path. The team instead confirms a target datum, adjusts preparation allowances within the approved systems and moves the material junction to the kitchen opening. Door undercuts and cabinet plinths are then checked against the revised schedule before anything is ordered.

                Check the details most affected by a few millimetres

                Small level changes can affect more than appearance. Entrance doors may have limited clearance; internal doors can need controlled undercuts; sliding tracks, balcony thresholds and bathroom entries may have fixed relationships; dishwashers and refrigerators need to remain removable; and kitchen worktop heights depend on cabinet and finished-floor assumptions. Skirtings and wall panelling also reveal inconsistent levels. Put these interfaces on the schedule and name who signs them off. Do not alter fire doors, waterproofing, drainage or shared-building interfaces without the appropriate specialist and building approvals.

                  The pre-order checklist

                  The floor decision is ready for procurement when the room schedule, physical samples and interface details tell the same story. Building-management conditions should be checked early because they may affect acoustic layers, working methods, delivery or approvals. Product orders should allow for the confirmed layout and supplier guidance, while keeping uncertainty visible rather than hiding it inside a broad contingency.

                  • Existing levels are surveyed against one datum
                  • Complete build-ups are recorded for every room
                  • Unknown substrates have an investigation plan
                  • Door, balcony, wet-area and kitchen interfaces are checked
                  • Threshold locations and profiles are agreed
                  • Building-management requirements are recorded
                  • Final product data replaces planning allowances before order

                    Limitations and site verification

                    A planning schedule cannot confirm concealed substrate condition before access is available. Local hollows, previous repairs, moisture issues or unexpected layers may require a revised preparation scope. This article also cannot specify acoustic performance, waterproofing, movement joints or transition geometry for a particular building. Those decisions belong to the relevant designer, contractor, supplier and building-management process. Dubai Municipality’s building guidance and Universal Design Code are useful official references, but project documents and product instructions remain essential.

                        A useful next step

                        Ask for a one-page finished-floor level schedule supported by a marked plan and two or three key threshold details. Review it before demolition, update it when the substrate is exposed and freeze it before flooring, doors, kitchens or skirtings are released for manufacture. That short sequence keeps visual choices connected to the physical apartment and makes later changes easier to identify and price without guessing.

                            Sources & further reading

                            Make this useful for your project.

                            A review of your property and priorities can turn general guidance into a defined brief.

                            Explore Apartment flooringDiscuss your project
                            Return to the journal